Schedule Thursday night bread production
You are the Assistant Bakery Supervisor at Shepparton.
What has happened
A supermarket promotion has lifted Friday orders for the 700 gram white sandwich loaf by eighteen percent, on top of the normal wholemeal and multigrain volumes. Thursday night shift must produce everything for the Friday morning dispatch window. Slicer 1 is under preventive maintenance after the plastic fragment complaint, so only slicer 2 is available. The bread line has fixed mixing, proving and baking times for each dough and the multigrain seeds require a changeover before white runs after it. Jo Tran wants a schedule that gets every order out in full and on time, plus a stock check and order for flour, yeast and improver.
Deliverables
- Thursday night production schedule
- Ingredient stock check and order
- Planned batch records
- Cover note to the Bakery Manager
Documents to use
Systems to use
Production Batch Records
Every food, beverage and pharmaceutical batch from planning to release, with line, quantity, status and the notes that support release.
Raw Material Receipts and Stock
Every inbound lot of raw material and packaging with supplier, quantity, allergen status and quarantine or release status.
Maintenance and Calibration Requests
Breakdown, preventive, calibration and hygienic design requests on plant and instruments at all three sites.
Units of competency
Current on training.gov.au for the Food, Beverage and Pharmaceutical as at 10 September 2026.
FBPRBK3012Schedule and produce bread productionFBPHVB3017Operate a bread dough mixing and development processFBPHVB3013Operate and monitor a baking processFBPRBK3016Control and order bakery stockQualifications
FBP31121Certificate III in High Volume BakingFBP30421Certificate III in Bread BakingWhat to look for
Evidence guide
Check the arithmetic from orders to mixes, the sequence reasoning around the seed changeover, the slicer capacity constraint being applied rather than ignored, and the stock check drawing on the receipts system. The schedule must allow time for critical control point checks and the cover note must state risks plainly.